We successfully reduced over-excavation in Fresnillo, Mexico

Jun 29, 2025

At our project in Fresnillo, Mexico, we successfully reduced over-excavation from 25% to 7%, significantly outperforming the industry benchmark of 10%. This result reflects a highly precise execution carried out under demanding conditions, with a strong focus on quality control, operational efficiency, and client commitment.

During execution, we achieved an outstanding performance rate of over 90 meters per month in a single negative ramp with a single heading, enabling the development of new mining areas for our client. In addition, we were pioneers in carrying out high-complexity negative excavations, operating in temperatures above 35°C while maintaining quality standards and a positive work environment.

This milestone reaffirms our ability to take on high-level technical challenges and actively contribute to our clients’ operational continuity—with safety, precision, and long-term vision.